Test Report:
Application flow and its test status:
1. List all products - Status : FINISHED AND TESTED.
2. User is able to add products to the shoppingkart - Status : FINISHED AND TESTED.
3. User proceeds to checkout the shoppingkart - Status : FINISHED AND TESTED.
4. User enters its personal information like address, name, email - Status : FINISHED AND TESTED.
5. User proceeds to payment page - Status : FINISHED AND TESTED.
6. System calculates the following information for the delivery:
* Distance
* Drone Delivery Costs - if applicable
* Drone Delivery Date
* Drone Delivery Estimated Flight Duration
* Normal Post Costs
* Normal Post Delivery Date
* Express Post Costs
* Express Post Delivery Date
* Payment Options
- Status : FINISHED AND TESTED.
7. User chooses a delivery and payment method Finish the order- Status : FINISHED AND TESTED.
8. New order is created in the DB - Status : FINISHED AND TESTED.
9. System prepares the order - Status : FINISHED AND TESTED.
10. System sends a notification about the order status - Status : FINISHED AND TESTED.
11. System dispatches the order and send the user a notifications about it - Status : FINISHED AND TESTED.
12. System updates the KPI - Status : FINISHED AND TESTED.