Project 10

Project Name: 
Private Dancers
Process Model
Modeling Tool: 
Camunda
BPMN 2.0 Model (.bpmn): 
BPMN 2.0 Model (.pdf): 
Effort Process Model: 
15hrs
Workflow Implementation
Execution Tool: 
Camunda BPM
Test Report: 
After the necessary tests during development (roughly 30-40% of development time overall) we tested our system local before deploying it. Test Cases 1-8 - Different email adresses - Different combinations of expercience levels & dance courses => Email notifications received and content is valid => OK Test Case 9-10 - Leaving required fields empty is not possible => OK - Submitting questionnaire without song requests => OK Test results - System works as excpected - Email notifications are sent as expected - Dance course proposal suit the customer's needs
Effort Implementation: 
12hrs
12hrs
16hrs
8hrs
12hrs